Elements in a Contract 22
In
deciding whether the plaintiff is entitled to damages for a breach of contract
the court will take into account two factors: -
i)
Causation
ii)
Remoteness
Causation
In
order for the plaintiff to be awarded damages the defendant must have caused
the damage. The damage must be actual and tangible as opposed to something that
could or may have caused damage. It however need not be the sole factor that
caused the damage.
When
looking into causation the courts will look into the chain of causation or the sequence
of events that led to the damage and in order for the plaintiff to be awarded
damages there must not be a break in the chain of causation i.e. the damage
must be a direct consequence of the defendant’s actions.
In
Monarch Steamship Co Ltd v Karlshamns Oljefabriker (1949) the defendants’ ship
was chartered to carry soya beans from Manchuria to Sweden. The defendants in
the contract had agreed to provide a seaworthy vessel but the ship developed
problems and there was a delay due to repairs in Egypt. Once the repairs were
completed the ship set sail for Sweden but by then the Second World War had
started and the Royal Navy ordered the ship to sail to Glasgow instead.
The
plaintiffs organized for the cargo to be shipped from Glasgow to Sweden and
brought an action against the defendants. The defendants argued that that the
ensuing war had broken the chain of causation but the court ruled otherwise. It
was not the war that caused the delay but rather the ship’s un-seaworthiness
and that it (the un-seaworthiness) was the dominant cause for the delay.
It
is worth comparing the decision in Monarch Steamship Co Ltd v Karlshamns
Oljefabriker (1949) with that in Quinn v Birch Bros (builders) Ltd (1966). The
plaintiff, in the latter case, was an independent subcontractor who undertook
plastering work for the defendants. The defendants had a contractual obligation
to supply the equipment that was necessary for the subcontractor to carry out
his work efficiently but failed to do so.
As
a result, the plaintiff found a folded trestle and stood on it to complete his
work. The trestle gave way and the plaintiff was injured in the accident that
followed. The plaintiff sued.
The
court held that it wasn’t the defendants’ breach of contract that had caused
the accident but rather the plaintiff’s decision to use unsound equipment.
The
use of an item that was not in the terms of the contract or the plaintiff’s
choice to use an item that would not be otherwise used in the manner that it
was had broken the chain of causation and the defendant was therefore not
liable.
Remoteness
Once
it is established that the defendant did indeed cause the plaintiff damage by
breaching a term of the contract, the courts will look into the aspect of
remoteness.
The
rules with regards to remoteness in contract cases were given in the leading
case of Hadley v Baxendale (1854). The plaintiffs, mill owners, commissioned
carriers to ferry a crankshaft for repair. The mill could only be operated with
the crankshaft in place and until such time that the crankshaft was replaced,
the mill would remain idle. The carriers agreed to return the crankshaft within
a stipulated time but because of their negligence the crankshaft was returned
to the plaintiffs a week later than expected. The plaintiff sued for the loss
of profits incurred between the agreed time of delivery and the actual time of
delivery. It was held that in order for damages to be awarded for a breach of
contract: -
i)
It must be damage arising from a breach of the terms of the contract that may
be considered reasonable and
ii)
The damage should be in the contemplation of both parties to the contract, at
the time the contract was entered into, as a likely result of a breach.
Because
the defendants were unlikely to contemplate the result of the breach as the
mill not being able to operate i.e. the second of the above two limbs, they
were not liable.
The fact that a crankshaft would cause a mill to come to a standstill was not something that would be within the contemplation of the defendants and under normal circumstances it would be fair to say that the plaintiffs, considering the importance of the crankshaft, would have had a spare or would have made arrangements to acquire a temporary crankshaft until theirs was returned.
Comments
Post a Comment